Capacity Booking
Capacity booking - What?
| Capacity products | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Yearly | Quarterly | Monthly | Daily | Within-day | |||||||
| Bundled | Unbundled | Bundled | Unbundled | Bundled | Unbundled | Bundled | Unbundled | Bundled | Unbundled | ||
| Frim | Yes | Yes | Yes | Yes | Yes | Yes | Yes | Yes | Yes | Yes | |
| Interruptible | ✖ | Yes | ✖ | Yes | ✖ | Yes | ✖ | Yes | ✖ |
Yes* |
|
| Capacity products | |||
|---|---|---|---|
| Yearly | |||
| Bundled | Unbundled | ||
| FIRM | Yes | Yes | |
| INTERRUPTIBLE | ✖ | Yes | |
| Quarterly | |||
| Bundled | Unbundled | ||
| FIRM | Yes | Yes | |
| INTERRUPTIBLE | ✖ | Yes | |
| Monthly | |||
| Bundled | Unbundled | ||
| FIRM | Yes | Yes | |
| INTERRUPTIBLE | ✖ | Yes | |
| Daily | |||
| Bundled | Unbundled | ||
| FIRM | Yes | Yes | |
| INTERRUPTIBLE | ✖ | Yes | |
| Within-day | |||
| Bundled | Unbundled | ||
| FIRM | Yes | Yes | |
| INTERRUPTIBLE | ✖ | ✖
(exception: Beregdaróc 800) |
|
Bunded capacity: bounded capacity on both sides of a given interconnection point based on CAM NC (one auction, two contracts)
*The product can be booked via capacity auction for VIP Bereg HU>UA network point and via overnomination at Mosonmagyaróvár HU>AT network point and other network points, where the firm capacity is sold out.
Capacity booking - Auction calendar
The Auction calendar regarding capacity auctions between 1st March 2024 and 28th February 2025 is accessible HERE .
The Auction calendar regarding capacity auctions between 1st March 2024 and 28th February 2026 is accessible HERE .
The capacities to be auctioned via the Regional Booking Platform are accessible in the RBP Portal in all cases.
Capacity booking - Where?
| Regional Booking Platform |
|---|
| Internet-based, electronic capacacity trading platform |
| Capacity allocation mechanisms regarding 459/2017/EU (CAM NC) |
| Free access to network users |
| Electronic certificate-based registration and access |
| RBP Application: RBP securely accessible software environment |
| RBP Portal: RBP internet-based openly accessible publication and information website |
| Test environment of RBP Application |
| Applicable rule: Operational Rules of the RBP |
| Applied time zone: UTC (UTC-CET difference is in summer -2, in winter -1 hour) |
| Network user connecting: by concluding the Network User Membership Agreement |
Capacity booking - When?
| According to Auction Calendar |
|---|
| Legal background: ENTSO-G Auction calendar, Hungarian Gas Act, Implementation Decree of Hungarian Gas Act |
| Publication of auction data: RBP Portal |
Capacity booking - How?
| Via Capacity auction | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
Ascending Clock algorithm |
Uniform Price algorithm |
||||||||||
Yearly capacity |
Quarterly capacity |
Monthly capacity |
Daily capacity |
Within-day capacity |
|||||||
Several bidding rounds:- First bidding round: 3 hours- Each additional round is 1 hour, including 1 hour break- Bidding rounds run on working days between 9.00 and 18.00 |
On bidding round: 30 minutes |
||||||||||
Auctions start in the afternoonpreceding the given gas day |
Auctions start:four hours before the start of the product |
||||||||||
For each bidding round, the reserve price is given in % |
Freely setting up the price, no price steps,Evaluation of bids by price, the highest price ranking first |
||||||||||
Large Price Step (LPS), Small Price Step (SPS) |
It is possible to submit Minimum quantity |
||||||||||
LPS is the integer multiple of SPS |
Network User may submit 10 bids as a maximum |
||||||||||
Purpose of LPS is to shorten the auction processPurpose of SPS is to maximize sold capacity |
Clearing price: the price of lowest successful bid |
||||||||||
Further info: CAM NC, Operational Rules of RBP |
|||||||||||
| Via Capacity auction | |||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| Ascending Clock algorithm | |||||||||||
| Yearly capacity | Quarterly capacity | Monthly capacity | |||||||||
| Several bidding rounds: - First bidding round: 3 hours - Each additional round is 1 hour, including 1 hour break - Bidding rounds run on working days between 9.00 and 18.00 |
|||||||||||
| For each bidding round, the reserve price is given in % | |||||||||||
| Large Price Step (LPS), Small Price Step (SPS) | |||||||||||
| Purpose of LPS is to shorten the auction process Purpose of SPS is to maximize sold capacity |
|||||||||||
| Uniform Price algorithm | |||||||||||
| Daily capacity | Within-day capacity | ||||||||||
| On bidding round: 30 minutes | |||||||||||
| Auctions start in the afternoon preceding the given gas day |
Auctions start: four hours before the start of the product |
||||||||||
| Freely setting up the price, no price steps, Evaluation of bids by price, the highest price ranking first |
|||||||||||
| It is possible to submit Minimum quantity | |||||||||||
| Network User may submit 10 bids as a maximum | |||||||||||
| Clearing price: the price of lowest successful bid | |||||||||||
| Further info: CAM NC, Operational Rules of RBP | |||||||||||
Capacity booking - At what cost?
| At capacity fee optional auction fee |
|---|
Tariffs and fees 2024 |
Tariff calculator from 1 October 2024 |
|
Clearing fee = reserve price (tariff) + auction fee (in case of oversubscription) |
Other fees related to using of capacities |
Capacity booking - Under what conditions?
| Conditions of auction participation | |||||||||
|---|---|---|---|---|---|---|---|---|---|
|
Proper financial background. General information about securities: Risk management systemFor gas year 2024/2025: Security calculator for yearly capacities, Security calculator - quarterly |
|||||||||
| Contractual background: RBP Registration, Network User Membership Agreement, Network Usage Framework Contract, till 15.00 2 working days prior to the given auction (IP and RBP registration) Signing of Amendement No. 1 of the Network User Membership Agreement in the case of a planned transaction at the Mosonmagyaróvár interconnecton point |
|||||||||
| Submission of trading licence or limited trading licence issued by the Hungarian Energy and Public Utility Regulatory Authority (MEKH) till 15.00 2 working days prior to the given auction | or | Declaration in case of transit through Hungary or in case of stroage in the underground gas storage facility - point II.5.6.2.(d) of BC | |||||||
| Obtaining clearing membership and clearing right at KELER CCP | |||||||||
Capacity booking - Cases of capacity modification
| RBP | IP |
|---|---|
Bilateral transactions:
|
Customer migration:
|
Capacity market transactions:
|
Capacity transfer:
|
Result of CMP:
|
Result of CMP:
|
Capacity conversion:
|
Capacity booking - Cases of special capacity booking
| Overnomination |
|---|
| At cross border and storage points |
| Transaction resulting interruptible within-day capacity booking |
| Where: Informatic Platform |
| 10 million HUF financial limit as a minimum |
| Incremental capacity auction |
|---|
| A process that leads to capacity booking for a non-existent facility through standard CAM NC auctions. |
| Info: kap@fgsz.hu |